Mathematics

1. A team of 2 men and 5 women completed one –fourth of a job in 3 days. After 3 days another man joined the team and they took 2 days to complete another one –fourth of the job. How many men can complete the whole job in 4 days?

[BB Assistant Director-2014 : 2014]

1

2
Answer
Comments